Ringwood Station and Interchange Upgrade
Cost
$66 million
Timeframe
Start: September 2014
Complete: early 2016
Current works taking place at Ringwood Station
Works to upgrade Ringwood Station and the bus interchange are progressing well.
Platforms 1 and 2 were closed for three weeks in July/August so that works could be undertaken to resurface Platform 1, relocate the 1891 heritage listed timber station building on Platform 1, and install new ramps and stairs connecting Platforms 1 and 2 to the new pedestrian concourse. Train passengers now access Platforms 1 and 2 through new Myki gates located on the concourse.
Relocation of Ticket Office
The Ticket Office at the entrance to Platform 3 will be temporarily closed while the station building is upgraded. Tickets will be available from the new Ticket Office on the pedestrian concourse. At project completion, there will be two ticket offices - one on the concourse, the other at the entrance to the station building on Platform 3.
Temporary carpark closure
The car park on Station Street is temporarily closed until the end of October.
Alternative parking areas are available on the south side of Maroondah Highway, just east of Warrandyte Road and at Costco on Market Street in Ringwood. Parking is still available at the Thanet Court car park.
Regular carpark users will be kept informed of carpark closures and alternative parking options via posters at the Station Street carpark and announcements at the station. Rail customers are encouraged to use alternative transport to the station while works to upgrade the station are being undertaken.
Download the map showing the location of alternative carparks (JPEG) 512kB
Bus stop locations
All buses currently depart and drop off at stops along Maroondah Highway and in the temporary bus interchange in Railway Place. Maps are displayed throughout the station precinct showing the location of bus stops for each bus route. Directional signage is also in place to guide customers to their bus stops.
Download the Ringwood bus interchange map (JPEG) 277kB
Upcoming works at Ringwood Station
Over the coming months:
- the new cycling lanes on Maroondah Highway will be coloured bright green and line marked to provide a safer environment for cyclists. This will include provision of Advance Stop Lanes (otherwise known as bike boxes) at the intersection of Maroondah Highway and Ringwood Street, and Maroondah Highway and Warrandyte Road
- the station buildings will be refurbished to provde modern and upgraded facilities for station staff
- the station carpark on Station Street will be resurfaced and fitted with new lighting, signage and CCTV cameras
- the new station forecourt will start to take shape. The new forecourt will be virbrant and accessible with improved safety features including additional lighting and CCTV.
Project description
The $66 million upgrade of the Ringwood Station precinct will deliver modern, integrated transport facilities to Ringwood. The upgrade will create a safer, more accessible and attractive place for people to live, work and visit.
VicRoads is managing project design and construction on behalf of Public Transport Victoria.
Project benefits
The project includes:
- an upgrade to Ringwood Station to provide full accessibility and improve amenity and shelter for customers
- a new pedestrian concourse providing 24-hour access over the rail line
- an upgrade of the heritage-listed station buildings
- reconstruction and expansion of the bus interchange
- new toilet facilities and waiting areas
- creation of a new landscaped station forecourt
- increased safety with additional lighting and CCTV
- a new signalised pedestrian crossing of Maroondah Highway, with more frequent crossing opportunities
- improved pedestrian and cycling facilities along the Maroondah Highway and Station Street
- improvements to the road environment in central Ringwood to create a 'boulevard' between Ringwood Street and Warrandyte Road.
Concept design
The project will transform the station precinct. Existing station buildings will be upgraded with more comfortable passenger facilities, new ramps, lifts and escalators will be installed between the platforms and a new concourse and forecourt will be created. The bus interchange will also be reconstructed and expanded and the Maroondah Highway pedestrian crossing will be improved.
Download the station precinct and concourse area layout (PDF) 580kB
Download the station precinct and concourse area layout changes - accessible (DOC) 17kB
Download the station concept designs (PDF) 227kB
Contact us
For more information, please call Public Transport Victoria on 1800 800 007 (6am - midnight daily).
You can also email the project team at [email protected]